Written by Chloe
Marie – Research Specialist
In May of 2017, we wrote three
articles addressing the then-pending
and approved
applications for LNG Export Projects in the United States. Since that time,
many legal developments have occurred and so we will once again provide a
discussion of LNG export developments through a planned five-part series. The
first two articles in the series will address approved applications for LNG
export projects in the United States with the first
article providing an overview on the development of six projects in
Louisiana that have been approved by both the Federal Energy Regulatory
Commission (FERC) and the U.S. Department of Energy (DOE) and this article
focusing on approved projects located in Texas and Georgia. Our next two
planned articles will address the status of pending LNG Export Project
applications, and our final article in the series will provide an overview of LNG
export projects that have moved beyond the mere application stage and are
currently in operation.
Texas:
The Stage 3 LNG Project (FERC CP18-512; CP18-513)
The Stage
3 LNG Project proposes to expand the existing Corpus Christi
Liquefaction Project located on the La Quinta Channel of Corpus Christi Bay in
San Patricio County, Texas, which is currently under construction. The Stage 3
LNG project would include the construction and operation of seven additional
midscale liquefaction trains and one LNG storage tank. According to Corpus
Christi Liquefaction Stage III, LLC, this project “would increase the expected
aggregate nominal LNG production capacity at the Liquefaction Project to
approximately 23 mtpa.”
Corpus Christi
Liquefaction Stage III, LLC filed an application with FERC under section 3 of
the Natural Gas Act (NGA) to site, construct, and operate the Stage 3 Project
on June 28, 2018. FERC expects to issue a final decision in late June 2019, as
stated in its Revised
Schedule for Environmental Review of the Stage 3 Project dated
February 2019. In March 2019, FERC issued an Environmental
Assessment for the project and concluded that “approval of the
Project, with appropriate mitigating measures, would not constitute a major
federal action significantly affecting the quality of the human environment.”
In addition,
Corpus Christi Liquefaction Stage III, LLC sought
authorization from DOE on June 29, 2018, to export approximately 11.45 million
metric tonnes per annum from the proposed project to FTA and NFTA countries.
This application is still under review by DOE.
The Freeport LNG Liquefaction Project (FERC docket
CP12-509; CP15-518)
The Freeport LNG
Liquefaction Project would expand the liquefaction capacity of the existing
Quintana Island terminal near Freeport, Texas, by 15 million metric tons per
annum and would add three liquefaction trains to the current infrastructure.
Construction of the three liquefaction trains started in November 2014 and,
according to Freeport LNG, the three trains are expected to start commercial
operations between Q3 2019 and Q2 2020.
Freeport LNG received
approval to export up to 511 Bcf of natural gas per year to FTA countries in
February 2012. FERC granted
authorization to proceed with the Liquefaction Project in July 2014, and DOE allowed
export of LNG to NFTA countries for up to 5.74 Bcf per year in November
2014.
The Freeport LNG Train 4 Project (FERC docket
CP17-470)
In June 2017,
Freeport LNG filed an application under NGA section 3 with FERC to construct and
operate an additional liquefaction train (Train 4) at the existing Quintana
Island terminal. In March 2018, Freeport LNG requested
authorization from DOE to export LNG to NFTA countries for up to 0.72 Bcf per
day.
Most recently, on
May 17, 2019, FERC issued
an order authorizing construction of the proposed Freeport LNG
Train 4 Project. FERC announced
in a Press Release that this “project will allow [Freeport LNG] to liquefy for
export the equivalent of an additional 0.74 billion cubic feet of natural gas
per day from the site.”
Interestingly,
FERC Commissioner Cheryl A. LaFleur wrote
in a concurring statement published on May 16, 2019, that she believed “the
Train 4 Project is not inconsistent with the public interest” while discussing concerns
over FERC’s failure to analyze the significance of the Project’s GHG emissions
on the human environment. She stated that FERC’s “general refusal to grapple
with the significance of GHG emissions creates an additional risk here, as the
Sierra Club challenges the Commission’s decision to issue an EA instead of an
Environmental Impact Statement (EIS). Sierra Club contends that the project’s
impacts are significant in the context of climate change and its contribution
to GHG emissions.”
The Golden Pass LNG Export Terminal Project (FERC
docket CP14-517)
The Golden
Pass LNG Export Terminal Project would add liquefaction and export
capabilities to the existing Golden Pass LNG import terminal near Sabine Pass,
Texas, including three liquefaction trains each capable of producing up to 5.2
million metric tons per annum together with associated treatment, power and
utility systems as well as interconnections to existing import facilities and
controls.
In September 2012,
Golden Pass Products, LLC, a subsidiary of Qatar Petroleum International, obtained
authorization from DOE to export up to 740 Bcf per year of natural gas to FTA
countries and, on December 21, 2016, were granted
approval from FERC to construct and operate the export terminal project. In
April 2017, Golden Pass Products, LLC, subsequently received permission to
export LNG for up to 808 Bcf per year to NFTA countries.
On February 5,
2019, Golden Pass Products, LLC declared
in a Press Release that it would begin construction as Qatar Petroleum secured
a final investment decision with ExxonMobil. Golden Pass Products, LLC, also
awarded the Engineering, Procurement and Construction (EPC) contracts for the
project to a joint venture comprised of Chiyoda International Corporation,
McDermott International Inc., and Zachry Group.
The Port Arthur Liquefaction Project (FERC docket
CP17-20)
The Port Arthur
Liquefaction Project proposes the construction and operation of two
natural gas liquefaction trains capable of producing up to 13.5 million metric
tons per annum, up to three LNG storage tanks and ancillary support facilities
to liquefy and load LNG onto ships. The Liquefaction Project will be located
along the Sabine-Neches ship channel in Texas.
In August 2015,
Port Arthur LNG, LLC, a subsidiary of Sempra LNG & Midstream, received
authorization from DOE to export up to 517 Bcf of natural gas per year to FTA
countries. Most recently, FERC granted Port Arthur LNG, LLC, approval to site,
construct, and operate the Liquefaction Project on April 18, 2019, following
the issuance of the Final
Environmental Impact Statement (FEIS) in January 2019. On May 2,
2019, DOE allowed
LNG export to NFTA countries for up to 698 Bcf per year.
On May 21, 2019,
Port Arthur LNG, LLC announced
in a Media Release that Sempra LNG and Aramco Services Company, subsidiaries of
Sempra Energy and Saudi Aramco, respectively, entered into a heads of agreement
(HOA), which “anticipates the negotiation and finalization of a definitive
20-year liquefied natural gas (LNG) sale-and-purchase agreement (SPA) for 5
million tonnes per annum (Mtpa) of LNG offtake from Phase 1 of the Port Arthur
LNG export project under development.”
Georgia:
The Elba Liquefaction Project (FERC docket no.
CP14-103)
The Elba
Liquefaction Project involves the expansion of the existing Elba Island LNG
terminal located on Elba Island, Chatham County, Georgia. In March 2014, Elba
Liquefaction Company, LLC, and Southern LNG Company, LLC, filed a joint
application under NGA Section 3 with FERC to construct and operate the new LNG
facilities. FERC granted
approval of the Liquefaction Project on June 1, 2016.
DOE received
applications in May and August 2012 from Southern LNG Company, LLC, to export
up to 0.5 billion cubic feet of natural gas per day to FTA and NFTA countries,
respectively. DOE granted authorization for such export to FTA
countries in June 2012 and then to NFTA
countries in December 2016. Construction of the Elba Liquefaction
Project began in November 2016.
On March 1, 2018,
Southern LNG Company, LLC filed an application
with DOE to obtain a blanket authorization for the export of up to 255 Bcf of
natural gas from the Elba Liquefaction Project on a short-term basis prior to
full commercial operations. DOE allowed
such export on July 6, 2018, to FTA and NFTA countries over a two-year period.
References:
The Stage 3 LNG Project
The Freeport LNG Liquefaction Project
The Freeport LNG Train 4 Project
The Golden Pass LNG Export Terminal Project
The Port Arthur Liquefaction Project
The Elba Liquefaction Project
Additional Resources:
This
material is based upon work supported by the National Agricultural
Library, Agricultural Research Service, U.S. Department of Agriculture.
No comments:
Post a Comment