Written by Chloe Marie – Research Fellow
This article is intended to provide an overview of the current status of
the Constitution pipeline project as well as recent legal developments related
to construction activities on the project.
The Constitution pipeline is a 124-mile new
project aimed at facilitating the delivery of natural gas to markets in New
York and New England. More precisely, the pipeline would transport up to
650,000 dekatherms of natural gas per day from facilities in Susquehanna
County, in northern Pennsylvania, to connect with the Iroquois Gas Transmission
and Tennessee Gas Pipeline systems in Schoharie County, New York.
Constitution Pipeline, LLC, a subsidiary of Williams Partners L.P.
operates the pipeline project, and on June 13, 2013, filed an application with
the Federal Energy Regulatory Commission (FERC) for a certificate of public
convenience and necessity. On October 24, 2014, FERC issued a Final Environmental Impact
Statement for the proposed project and concluded that “construction and
operation of the [Constitution pipeline] would result in some adverse
environmental impacts, but these impacts would be reduced to
less-than-significant levels.”
Subsequently, on December 2, 2014, FERC issued a Certificate of Public Convenience and Necessity to Constitution Pipeline Company, LLC, approving the construction and
operation of the interstate Constitution Pipeline project. On April 27, 2015,
Constitution Pipeline Company, LLC, filed a Section 401 Water Quality
Certification with the New York Department of Environmental Conservation (DEC)
for the proposed pipeline project.
Based on its 2016 spring forecast, Constitution Pipeline, LLC, anticipated
an in-service date within the range of the fourth quarter of 2016 to the second
half of 2017. The pipeline construction, however, has been impacted due to
recent legal developments primarily relating to the routing of the pipeline.
On April 22, 2016, the New York DEC issued a Press
Release denying Constitution Pipeline Company LLC’s application
for a Section 401 Water Quality Certification. In support of this decision,
Chief Permit Administrator John Ferguson declared that “although the Department repeatedly
asked Constitution to analyze alternative routes that could have avoided or
minimized impacts to an extensive group of water resources, as well as to
address other potential impacts to these resources, Constitution failed to
substantively address these concerns.”
On May 16, 2016, Constitution Pipeline Company, LLC, filed a petition
for review of the New York DEC’s denial of Constitution’s application for a
Section 401 Water Quality Certification in the U.S. Court of Appeals for the
Second Circuit (see docket no. 16-1568).
Among other arguments, Constitution Pipeline Company, LLC, alleged that the New
York DEC exceeded the statutory time limitations to review the Section 401
application and, as a result, waived its right to issue a Section 401 Certification.
On August 18, 2017, the Court of Appeals held that it lacked jurisdiction over
the timeliness of New York DEC’s decision and dismissed the petition in part.
With regard to the merits of the case, the Court concluded that the state
agency’s denial decision “was not arbitrary or capricious.”
On September 1, 2017, Constitution Pipeline Company, LLC, filed a
petition for rehearing on the merits of the New York DEC’s denial of the
Section 401 Certification and claimed that “the panel should not have
prematurely ruled upon the merits of the Denial, but instead should have held
the proceedings in abeyance pending FERC’s determination on waiver.” The U.S. Court
of Appeals for the Second Circuit denied such petition on October 19, 2017.
In the meantime, on October 12, 2017, Constitution Pipeline Company, LLC,
filed a petition for declaratory order asking FERC to determine that the New
York DEC waived its authority to issue a water quality certification for the
Constitution Pipeline Project.
In an Order dated January 11, 2018, FERC denied
Constitution’s petition for declaratory order recalling that a waiver to issue
certification applies only when the state agency fails to act on an application
within one year and, referring to prior certification applications submitted in
August 2013 and May 2014 and then withdrawn, FERC pointed out that “by
withdrawing its applications before a year had passed, and by presenting New
York DEC with new applications, Constitution gave New York DEC new deadlines.”
As a result, FERC declared that “the record does not show that New York DEC in
any instance failed to act on an application that was before it for more than
the outer time limit of one year.”
On January 16, 2018, Constitution Pipeline Company, LLC, filed a petition for a writ of certiorari
seeking review of the U.S. Court of Appeals for the Second Circuit before the
U.S. Supreme Court (see docket no.
17-1009). In reviewing the Second Circuit Court’s decision, Constitution
Pipeline Company, LLC, asked the U.S. Supreme Court to answer whether New York
DEC exceeded its authority when denying Constitution’s application for a
Section 401 Water Quality Certification on the basis of insufficient
information regarding the proposed pipeline’s alternative routes and whether the
state agency interfered with FERC’s exclusive authority over the routing of
interstate natural gas pipelines.
Stay tuned for further legal developments!
Very Nice website. I recently engineered mine and that i was craving for some ideas and you gave me a number of. might i raise you whether or not you developed the web site by youself ? https://www.eliaandponto.com/michigan-auto-accident-lawyer/
ReplyDeleteGreat post, you have pointed out some great points , I also think this s a very excellent website. https://www.gpwlaw-mi.com/
ReplyDeleteHello we Can supply Aviation Kerosene, Jet fuel (JP 54-A1,5), Diesel (Gas Oil) and Fuel Oil D2, D6,ETC in FOB/Rotterdam only, serious buyer should contact or if you have serious buyers
ReplyDeletemy seller is ready to close this deal fast contact us below: now base email us severgazinvest@inbox.ru
PRODUCT AVAILABLE IN ROTTERDAM/ CI DIP AND PAY IN SELLER EX-SHORE TANK.
Russia D2 50,000-150,000 Metric Tons FOB Rotterdam Port.
JP54 5000,000 Barrels per Month FOB Rotterdam.
JA1 Jet Fuel 10,000,000 Barrels FOB Rotterdam.
D6 Virgin Fuel Oil 800,000,000 Gallon FOB Rotterdam.
E-mail: paveleriks@mail.ru
Phone via WhatsApp/
Call +79167856894
Best Regards