Written
by Chloe Marie – Research Fellow
This
article provides an update on the latest legal developments related to the Dakota
Access Pipeline. This article supplements the update that was posted to this
blog in November 2016.
U.S. Army Corps of Engineers
On
July 25, 2016, the U.S. Army Corps of Engineers granted Section 408 permission
allowing the proposed Dakota Access pipeline project to cross federal lands administered
by the Corps near Lake Oahe, North Dakota. This decision was accompanied by a
Finding of No Significant Impact (FONSI) based on an Environmental Assessment (EA)
issued on the same day. The Corps concluded that the proposed pipeline project
“is not injurious to the public interest” and stated that it had “coordinated
closely with Dakota Access to avoid, mitigate and minimize potential impacts of
the [proposed project] so that the pipeline would not impair the usefulness
of the projects and the impacts to the environment would be temporary and not
significant.” The Corps thus “determined that preparation of an Environmental
Impact Statement is not required.”
On September 9,
2016, however, the U.S. Department of Justice, together with the U.S.
Department of Army and the Department of the Interior issued a joint
statement declaring that, because of the importance of the
legal issues, “the Army will not authorize constructing the Dakota Access
Pipeline on Corps land bordering or under Lake Oahe until it can determine
whether it will need to reconsider any of its previous decisions regarding the
Lake Oahe site under the National Environmental Policy Act (NEPA) or other
federal laws.” On November 14, 2016, the Corps issued a statement indicating that “additional
discussion and analysis” is needed to better understand whether to grant Dakota
Access with an easement to access Corps-managed land near Lake Oahe.
Following this
statement, on December 4, 2016, the Corps denied the grant of such easement in
order to explore alternative routes for the Dakota Access pipeline crossing. Consequently,
the Corps issued on January 18, 2017, a Notice of Intent
to prepare an Environmental Impact Statement (EIS) in connection with Dakota
Access, LLC’s request for an easement to cross Lake Oahe. The Notice of Intent
informs that the Corps intends to prepare an Environmental Impact Statement
(EIS) in order to identify the potential impacts of the easement on the
environment and consider alternative routes.
President
Donald Trump released on January 24, 2017, a Presidential Memorandum
directing the Corps to consider whether to withdraw the Notice of Intent to
prepare an EIS. As a result, on February 8, 2017, the Corps granted an easement
to Dakota Access to install a portion of the pipeline below the Lake Oahe. The Press Release
issued at that time states that “the granting of this easement follows the
February 7th Secretary of the Army decision to terminate the Notice
of Intent to Perform an Environmental Impact Statement and notification to
Congress of the Army’s intent to grant an easement to Dakota Access for the
Lake Oahe crossing.”
The Yankton Sioux Tribe and Oglala
Sioux Tribe lawsuits
On
September 8, 2016, the Yankton Sioux Tribe filed a complaint for injunctive and
declaratory relief against the U.S. Army Corps of Engineers and the U.S. Fish
and Wildlife Service challenging, among other things, the Corps’ July 2016 EA
and FONSI as well as the March 2012 Nationwide Permits. The complaint states
that “of particular importance to [the Yankton Sioux Tribe] is the
location where DAPL crosses the James River” before adding that “from time
immemorial, the Yankton camped up and down the banks of the James River and as
a consequence, burial, cultural, and historical sites remain along the James
River that are at immediate risk of irreparable injury as a result of
Defendants’ actions and Dakota Access, LLP’s planned activities.”
Later on, the Oglala
Sioux Tribe also brought an action against the U.S. Army Corps of Engineers on
February 11, 2017, alleging that the pipeline crossing at Lake Oahe would
impair the Tribe’s water supply, part of the Mni Wiconi water pipeline. In
addition, the Tribe asked the Court for a declaration that “the EA/FONSI are
inadequate and that the Corps must complete an EIS that analyzes impacts to the
Tribe’s Treaty rights and its rights in the Mni Wiconi Project as required by
NEPA and the Mineral Leasing Act …”
On March 16, 2017,
the U.S. District Court granted the Corps’ motion to consolidate Yankton Sioux Tribe v. U.S. Army Corps of
Engineer, docket 1:16-cv-01796 and Oglala
Sioux Tribe v. U.S. Army Corps of Engineers, docket no. 1:17-cv-00267 with Standing Rock Sioux Tribe v. U.S. Army Corps
of Engineers, docket 1:16-cv-01534. All filings in these consolidated cases
are now only made in the Standing Rock docket.
The Standing Rock Sioux Tribe and
Cheyenne River Sioux Tribe lawsuit
On August 10, 2016, the Cheyenne River
Sioux Tribe filed a motion to intervene in support of the Standing Rock Sioux
Tribe pointing out that the pipeline construction will take place on ancestral
lands of the Cheyenne River Sioux Tribe, and thus the Corps should have
consulted the Tribe. The U.S. District Court later granted such motion allowing
the Cheyenne River to participate as a party in this ongoing litigation.
Since
our last article
dated November 2016 addressing the status of the Dakota Access pipeline
project, Dakota Access filed a motion for summary judgment on December 5, 2016,
seeking a declaration under the Declaratory Judgment Act that the Corps granted
the company an easement to construct, operate and maintain the Dakota Access
pipeline. Dakota Access argued that the Corps already received such easement on
July 25, 2016, through Section 408 permission to cross federal lands at Lake
Oahe and “that decision … is the
grant of a right-of-way.” Dakota Access added that “nothing authorizes the
Corps to invoke good policy after the process is complete, especially where the
Corps agrees that every legal requirement was satisfied in reaching an earlier
final decision.”
On
January 6, 2017, the Standing Rock Sioux Tribe, together with the Cheyenne
River Sioux Tribe and the Corps, filed motions to dismiss Dakota Access’
November 2016 cross-claim for failure to state a claim upon which relief can be
granted. The Corps pointed out that the administrative decision-making process
to grant an easement had yet to be completed under the Mineral Leasing Act.
Both Tribes alleged that the Corps did not render a final decision as to the
easement.
The
Corps also opposed Dakota Access’ motion for summary judgment and both Tribes
cross-moved for summary judgment. The Standing Rock Tribe essentially asked
whether Dakota Access already obtained the right to construct the pipeline on
Corps-managed lands near Lake Oahe under Section 185 of the Mineral Leasing Act
while the Cheyenne River Tribe alleged that there was no genuine issue of
material fact and that the Tribes were entitled to judgment as a matter of law. The court subsequently denied this motion for
summary for summary judgment as well as the cross-motions.
The
Cheyenne River Sioux Tribe filed a motion for preliminary injunction and a
temporary restraining order barring Dakota Access from construction and
drilling under Lake Oahe following the easement issued by the Corps on February
8, 2017. The U.S. District Court, however, denied the Tribe’s motion for
preliminary injunction on March 7, 2017, holding that “the extraordinary relief
requested is not appropriate in light of both the equitable doctrine of laches
and the Tribe’s unlikelihood of success on the merits.”
On
February 14, 2017, the Standing Rock Tribe filed a motion for partial summary
judgment requesting the Court to “hold unlawful and set aside” the granting of
the easement and related permit decisions on the grounds that the Corps failed
to prepare an EIS and thus violated the National Environmental Policy Act
(NEPA), that such granting is “arbitrary, capricious, and contrary to law,” and
that the Oahe crossing does not qualify for streamlined nationwide permit 12. A
few days later, the Cheyenne River Tribe also filed a motion for partial
summary judgment on February 22, 2017, asking the Court to declare that
issuance of section 408 permission was made in violation of the Flood Control
Act and Mineral Leasing Act, and that the Corps did not fulfill its duty to
consult with the Tribe “in a meaningful way pre-decisionally on any action that
has the potential to substantially affect trust resources or treaty rights.”
On
June 14, 2017, the U.S. District Court granted in part and denied in part the Standing
Rock Tribe’s Motion for Partial Summary Judgment, and granted in part and denied
in part the Corps’ corresponding Cross-Motion for Partial Summary Judgment. In
addition, the Court denied in part the Cheyenne River Tribe’s Motion for
Partial Summary Judgment and granted in part the Corps’ and Dakota Access’
Cross-Motion for Partial Summary Judgment. The Court explained that the Corps
failed to fully follow the NEPA process when it determined that the pipeline
project would not have a significant environmental impact and asked parties to
submit further briefing on the question whether or not the Corps’ EA should be
vacated.
To
this question, the U.S. District Court answered it in the negative in an Order &
Memorandum Opinion
dated October 11, 2017. The Court refused to halt further construction of the
pipeline finding that the Corps’ would be able to justify its previous decision
not to conduct a full environmental review. The Court, however, declared that
“compliance with NEPA cannot be reduced to a bureaucratic formality, and the
Court expects the Corps not to treat remand as an exercise in filling out the
proper paperwork post hoc.”
Stay
tuned for further legal developments!
This is very educational content and written well for a change. It's nice to see that some people still understand how to write a quality post! Radley Law
ReplyDeleteThis is the right blog for anybody who wants to search out out about this topic. You realize a lot its virtually arduous to argue with you (not that I actually would need…HaHa). You positively put a new spin on a topic thats been written about for years. Nice stuff, just nice! https://www.eliaandponto.com/michigan-auto-accident-lawyer/
ReplyDeleteYour talent is really appreciated!! Thank you. You saved me a lot of frustration. I switched from Joomla to Drupal to the WordPress platform and Ive fully embraced WordPress. Its so much easier and easier to tweak. Anyway, thanks again. Awesome domain! GPW Law
ReplyDeletePretty good post. I just stumbled upon your blog and wanted to say that I have really enjoyed reading your blog posts. Any way I’ll be subscribing to your feed and I hope you post again soon. Please coming site webstagram to see top hashtag on isntagram.
ReplyDelete